Skip to content
Investor Login

Investor Login Coming Soon

Secure investor access is being prepared for a future release.

M2 Process

M2 validates install completion, monitoring access, permitting, NEM application, final inspection evidence, and any change-order finalization.

Milestone Timing

FieldDetail
Begins WhenInstallation is complete and the partner can provide post-install photos, monitoring access, and permitting/inspection evidence.
Ends WhenMAC approves the post-install package and the project can proceed toward PTO and M3.
Common DelayMonitoring access, final inspection evidence, or change-order design/BOM materials are incomplete.

Sequence of Events

  1. Install complete
    Partner uploads install-complete photos and commissioned-system evidence.

  2. Monitoring access granted
    Partner adds Monitoring@getmacfinance.com to solar and battery monitoring platforms.

  3. Permitting package reviewed
    Partner submits permitting, NEM application, and passed inspection evidence.

  4. M2 approval clears PTO path
    MAC approves the post-install package and the project moves toward PTO and M3.

DocumentStatusSubmitted ByAbridged Notes
Install-Complete PhotosPartner-submitted
Required
EPC
Complete project photo set.
Required
EPC
Use Monitoring@getmacfinance.com.
Required
EPC
System registered and commissioned.
Conditional
EPC
Final design if change order occurred.
Bill of Material (BOM)Partner-submitted
Conditional
EPC
Final BOM if change order occurred.
City / County PermittingExternal-generated
Required
AHJ / EPC
City/county permit evidence.
NEM Utility ApplicationExternal-generated
Required
Utility / EPC
Utility NEM application.
Required
AHJ / EPC
Passed final building/electrical inspection.