M2 Process
M2 validates install completion, monitoring access, permitting, NEM application, final inspection evidence, and any change-order finalization.
Milestone Timing
| Field | Detail |
|---|---|
| Begins When | Installation is complete and the partner can provide post-install photos, monitoring access, and permitting/inspection evidence. |
| Ends When | MAC approves the post-install package and the project can proceed toward PTO and M3. |
| Common Delay | Monitoring access, final inspection evidence, or change-order design/BOM materials are incomplete. |
Sequence of Events
Install complete
Partner uploads install-complete photos and commissioned-system evidence.Monitoring access granted
Partner adds Monitoring@getmacfinance.com to solar and battery monitoring platforms.Permitting package reviewed
Partner submits permitting, NEM application, and passed inspection evidence.M2 approval clears PTO path
MAC approves the post-install package and the project moves toward PTO and M3.
Required Documents
Section titled “Required Documents”DocumentStatusSubmitted ByAbridged Notes
System Registered & Commissioned PhotoPartner-submitted
Required
EPC
System registered and commissioned.
Passed Final Building & Electrical InspectionExternal-generated
Required
AHJ / EPC
Passed final building/electrical inspection.
DocumentStatusSubmitted ByAbridged Notes
System Registered & Commissioned PhotoPartner-submitted
Required
EPC
System registered and commissioned.
Passed Final Building & Electrical InspectionExternal-generated
Required
AHJ / EPC
Passed final building/electrical inspection.